ExecPlan 001 — Implementation Roadmap: AquaCom Integration Gateway
Document type: ExecPlan (umbrella roadmap)
Status: Active
Created: 2026-10-06
Scope: Phases 0–14 (implementation specification §60) through the initial production release
Authoritative references: ARCHITECTURE.md · docs/product/software-specification.md · docs/product/codex-implementation-specification.md · docs/configuration/configuration-reference.md · docs/protocol/ (gap registry, operations registry, test vectors)
This is the umbrella plan: it sequences the whole implementation and records cross-phase decisions. Substantial individual features may spawn focused child ExecPlans in this directory (implementation specification §59); this roadmap remains the index. Per
ARCHITECTURE.md§1, role-authoritative documents win over any restatement here.
1. Purpose
Provide a single, gated execution path from the current documentation-complete, evidence-prepared repository state to the initial production release defined by software-specification.md §47 / implementation specification §74, such that:
- every implemented AquaCom behavior traces to verified evidence (
AGENTS.md,known-operations.md); - each phase ends in a working, testable repository state (implementation specification §79);
- the one open blocking decision (technology selection) is resolved explicitly and recorded before code begins;
- protocol gaps are consumed at the phase that needs them, with documented workarounds where possible.
2. Current state (2026-10-06)
Exists and verified:
- Complete, consistent documentation set: short-form
AGENTS.mdentry point;ARCHITECTURE.mdwith document precedence (§1) and invariants INV-001…INV-016;software-specification.mdwith requirement IDs AQG-001…AQG-030 and RFC-2119 keywords; agent-neutral implementation specification;configuration-reference.md. - Protocol evidence: authoritative source (AquaCom – RTU level, Rev 1.6, ITT Flygt AB, 2004) as PDF + markdown conversion in
docs/protocol/. docs/protocol/protocol-gaps.md— 10 entries (1VERIFY, 9OPEN), each with working hypotheses where applicable.docs/protocol/known-operations.md— OPS-001…OPS-012 registered with evidence sections, scope status, and an evidence-complete implementation order.docs/protocol/test-vectors.md— 35 source checksum vectors verified by recomputation against the §2.4 algorithm (including the §3.6.4 Wait-byte pair), framing/session vectors, 4 synthetic wraparound vectors, WGS/WGH/WGD decode scenarios, simulator scenario requirements.
Does not exist yet: src/, tests/, simulator/, schemas/, config/, CI, README.md, CHANGELOG.md, any implementation.
Open: technology selection (decision D-001 below) — the only blocking item.
3. Desired state
The initial production scope (implementation specification §74): verified live and historical AquaCom acquisition for multiple stations; canonical data model; live cache; historical pipeline with deduplication and durable spool; ≥1 queryable history repository; ≥2 independently configurable storage destinations; OPC UA Data Access + Historical Access with stable NodeIds and security on by default; diagnostics and structured logging; simulator; automated tests including restart recovery; configuration validation. Explicitly excluded: process control, setpoint writes, OPC UA HistoryUpdate, HA clustering (implementation specification §75).
4. Constraints
Hard rules that bind every phase (traceability in parentheses):
- Never invent AquaCom protocol behavior; evidence classes only (
AGENTS.md; implementation specification §3.1). - AquaCom logic only in
src/aquacom; OPC UA and storage never parse telegrams (INV-001/002/003). - Historical samples never update current state (INV-004); SourceTimestamp preserved (INV-005).
- OPC UA HistoryRead queries a repository, never the RTU (INV-006).
- Storage failure never stops live acquisition (INV-007).
- Stable StationId/PointId/NodeIds across restart, upgrade, rename, transport change (INV-008/009).
- Watermark advances on durable spool commit (INV-014); dedup correct across restart (INV-015).
- Out-of-order historical arrival supported (INV-013); missing-timestamp records quarantined (INV-016).
- Live acquisition priority over backfill (AQG-028); every queue bounded (ARCHITECTURE §51).
- Secure defaults; no secrets in the repo (
AGENTS.mdSecurity).
5. Open decisions
| ID | Decision | Blocks | Recommendation / resolution path |
|---|---|---|---|
| D-001 | Implementation language + OPC UA server stack | Phase 1 (all code) | The hard constraint is server-side Historical Access (Part 11) — far less commonly supported than Data Access. Run a HistoryRead smoke test per candidate before committing. Candidates in priority order: C#/.NET (OPC Foundation .NET Standard stack — reference HA implementation), Java/Milo (HA supported), Python/asyncua (fast development; verify HA server completeness first). |
| D-002 | Configuration format | Phase 0 (schema skeleton) | YAML — all examples in configuration-reference.md are already YAML. Low risk. |
| D-003 | First history repository technology | Phase 8 | Behind the HistoryRepository interface (ARCHITECTURE §25), so replaceable. Embedded (e.g. SQLite) minimizes external dependencies for the first release; external (PostgreSQL/TimescaleDB) remains a valid Phase 12+ sink. Decide at Phase 8 entry. |
| D-004 | Second storage sink technology | Phase 12 | NDJSON file archive is the lowest-risk second destination (config examples already use it). Decide at Phase 12 entry. |
| D-005 | CI platform | Phase 0 | Whatever the repository host provides; must run format/lint/static/unit/integration + schema validation without network access (implementation specification §57). |
| D-006 | Configuration schema technology | Phase 0 | JSON Schema if D-002 = YAML (standard YAML-schema validation path). |
Pre-implementation checklist (project owner, in order):
- Resolve D-001. I can build and run the HA smoke test for each candidate stack on request — a ~50-line HistoryRead server+client per candidate settles it empirically.
- PDF spot-checks (~30 min, recommended before Phase 3/6; non-blocking for Phases 0–2): confirm AQ-GAP-001(a) MCC type table, (b) WGS answer
mp1–mp128byte ranges, (e) whether §3.7 truly ends mid-telegram; AQ-GAP-002 whether the PDF definesalpmore explicitly; AQ-GAP-006 whether the MAT request really prints 557. - Confirm deployment target: OS/host, and whether field contact is TCP via terminal server (serial-over-IP) or direct serial — determines which Phase 2 transports to implement first.
What does not block starting: real RTU hardware or captures (the simulator drives Phases 0–13; every gap that would need a live capture has a documented workaround), aquacom.md consolidation, operations documentation (Phase 14).
6. Implementation sequence
6.1 Phase/gate overview
| Phase | Scope (§60) | Gate — exit criteria | Key gap dependency |
|---|---|---|---|
| 0 | Repository skeleton, CI, README/CHANGELOG, config schema skeleton | G0: CI green on placeholder test; schema validates the §72 minimal config; tree matches implementation specification §5 | — |
| 1 | Canonical core: StationId, PointId, CurrentValue, HistoricalSample, DataQuality, AcquisitionSource, config domain | G1: domain unit tests + serialization round-trips pass; identifier-stability rule enforced (rename ≠ new PointId); core has zero aquacom/opcua/storage imports |
— |
| 2 | Transport abstraction + mock transport; TCP first (serial-over-IP per deployment answer) | G2: connect/send/receive/timeout/reconnect tests pass; supports shared-medium arbitration (software-specification §5.1) | — |
| 3 | Codec framework: framing, checksum, Wait-byte stripping, validation, fixture framework | G3: 100 % of approved vectors green (AQ-CK-001…035, S1–S4, framing vectors AQ-FR-001…005); invalid telegrams rejected with diagnostics | AQ-GAP-001 (VERIFY items against PDF) |
| 4 | AquaCom simulator | G4: scripted WGS success/timeout/malformed/checksum-error/configurable values; no shared codec code (self-validation ban, §49) | — |
| 5 | Station/session manager | G5: multiple simulated stations; one failing station does not affect others; state machine per §18; configurable thresholds | — |
| 6 | Live acquisition: WGS decode → point mapping → scaling → CurrentValue | G6: simulator → CurrentValue with correct value, quality, timestamps (Source vs Received distinguished); scaling formula applied; alarm/point split via Nal |
AQ-GAP-002 (workaround: decode via Nal, alp diagnostic-only) |
| 7 | OPC UA live interface: DA, subscriptions, stable NodeIds, security | G7: OPC UA test client browses/reads/subscribes; NodeIds stable across restart; security None disabled |
— |
| 8 | Local historical repository (first queryable store) | G8: store / query interval / bounds / restart persistence behind the §25 interface | — |
| 9 | Historical pipeline: validation → dedup → durable spool → distribution | G9: duplicate submissions produce no duplicate records (idempotent across restart, INV-015); spool survives restart; out-of-order writes accepted (INV-013) | — |
| 10 | AquaCom historical acquisition: WGH retrieval, watermark, backfill state machine, throttling | G10: simulator's missing interval recovered after reconnect; watermark resumes from persistent state; backfill throttled so live polling stays responsive | AQ-GAP-003 (hypothesis: block value count from station CFG — validate against simulator) |
| 11 | OPC UA Historical Access: HistoryRead raw values, continuation | G11: HA client reads both originally stored and recovered values; continuation works; INV-006 test: HistoryRead never triggers AquaCom traffic | — |
| 12 | Second storage destination (sink abstraction) | G12: one HistoricalSample → repository + sink B; failure of B does not stop A | — |
| 13 | Store-and-forward resilience | G13: destination offline → history accumulates → delivered on restore; restart during backlog loses no acknowledged data (§53) | — |
| 14 | Production hardening: security, resource limits, performance validation, ops documentation | G14: §77 DoD reviewed item-by-item; §69 performance validation with capacity targets recorded | — |
| O-1 (optional, after 10) | WGD periodical reports (AQUACOM_REPORT) |
report day retrieved, scaled per point, NDA handled as missing-not-failed |
AQ-GAP-009 (documented defaults) |
6.2 Task mapping (implementation specification §79)
T001→P0 · T002→P1 · T003→P0/P1 (config model + schema validation) · T004→P2 · T005+T006→P3 · T007→P4 · T008→P6 (WGS, first verified live operation) · T009→P5/P6 · T010→P6 (current-state service) · T011→P7 · T012→P8 · T013→P9 · T014→P9/P13 (durable spool) · T015+T016→P10 (WGH + backfill state machine) · T017→P11 · T018→P12 · T019→P13 (full reconnect/backfill acceptance) · T020→P14.
Each task ends in a working repository state. Recommended task granularity: one §79-sized task per working session, each with the Goal / Files / Behavior / Constraints / Tests / Acceptance structure (§61).
6.3 Gap consumption schedule
| Gap | Consumed at | Handling |
|---|---|---|
| AQ-GAP-001 | before Phase 3 table implementations | VERIFY against PDF; 35 approved vectors already cover framing/checksum |
| AQ-GAP-002 | Phase 6 | workaround documented (decode via Nal); hypothesis strengthened by all four examples |
| AQ-GAP-003 | Phase 10 | hypothesis wired to station CFG; simulator validation; close on first real capture |
| AQ-GAP-004 | text points (none in initial scope) | deferred |
| AQ-GAP-005 | any time PDF text is available | transcribe long examples → recompute → approve as wraparound fixtures (synthetics cover the branch meanwhile) |
| AQ-GAP-006 | Phase 3 fixture import | use 540 once PDF-confirmed; verified answer vector approvable independently |
| AQ-GAP-007 | SCE handling (Phase 3/6) | payload treated as optional diagnostic, never parse-critical |
| AQ-GAP-008/009/010 | dialled lines / WGD / alarms | extension scope; not in initial release |
7. Files/components affected
src/{core,aquacom,history,storage,opcua,diagnostics,host}/ per ARCHITECTURE.md §6 and dependency direction §7 · tests/{unit,integration,protocol,opcua,history,acceptance}/ · simulator/ · fixtures/ (imported from docs/protocol/test-vectors.md) · schemas/ · config/examples/ · README.md, CHANGELOG.md · CI definition · documentation updates in docs/ as behavior lands (never after).
8. Data model changes
None yet — the canonical contracts are frozen in ARCHITECTURE.md §13–§14 and implementation specification §10–§13. Any contract change requires: update the role-authoritative document first, update dependents, update tests, record the decision here. The core module must compile without AquaCom/OPC UA/storage imports (enforced in CI from Phase 1).
9. Failure handling
The failure matrix of software-specification.md §35 / ARCHITECTURE.md §55 is normative: station failure isolates; storage failure isolates and buffers; OPC UA failure never stops acquisition; malformed telegrams are rejected with diagnostics; restart loses no acknowledged history. Each phase's tests must cover the failure modes it introduces (implementation specification §56 fault injection); every new failure mode gets a diagnostic (AGENTS.md Task completion).
10. Testing
- Pyramid per §50: deterministic unit/component tests dominate; integration via simulator; acceptance scenario at the top.
- Fixtures: imported only from
docs/protocol/test-vectors.md; approved fixtures immutable; new vectors require evidence and registry update (never delete). - Protocol tests run without external network (§57); simulator must not share codec code (§49).
- Restart-recovery tests at every phase that adds persistent state (§53).
- Bug fixes carry regression tests (AGENTS.md).
11. Migration/compatibility
Storage schemas versioned with explicit migrations; startup never silently destroys incompatible data; destructive migration requires administrative action (implementation specification §65). configVersion gating with explicit migration tooling (§66). OPC UA NodeId stability across releases (§68); configuration schema changes never force namespace changes (configuration-reference.md §71).
12. Progress
| Date | Entry |
|---|---|
| 2026-10-05 | Documentation set completed and made consistent; protocol evidence acquired (Rev 1.6 source); gap registry (10 entries), operations registry (OPS-001…012), and test-vector catalogue (35 verified vectors) created. Phase 0 documentation deliverables done. |
| 2026-10-06 | This roadmap created. Awaiting D-001 (technology selection) before Phase 0 code tasks. |
| 2026-10-06 | README.md and CHANGELOG.md created — the §5 repository-structure documentation items for Phase 0 are complete. Remaining Phase 0 deliverables: technology selection (D-001), code skeleton, CI, configuration schema. |
Update this log at every phase gate; spawn child ExecPlans for §59-triggering work and link them here.
13. Decisions log
| ID | Date | Decision | Reference |
|---|---|---|---|
| DR-001 | 2026-10-05 | Documentation unescaped, de-duplicated; single-source-of-truth precedence defined | ARCHITECTURE.md §1 |
| DR-002 | 2026-10-05 | AGENTS.md reduced to short entry-point form per its own spec §4/§6 |
AGENTS.md |
| DR-003 | 2026-10-05 | Watermark advances on durable spool commit, not final delivery | ARCHITECTURE.md §21, INV-014 |
| DR-004 | 2026-10-05 | Duplicate-conflict default REJECT_CONFLICT | software-spec §13 |
| DR-005 | 2026-10-05 | Deduplication correct across restart (persisted state or idempotent storage) | INV-015 |
| DR-006 | 2026-10-05 | Pipeline accepts out-of-order historical arrival; queries order by SourceTimestamp | INV-013 |
| DR-007 | 2026-10-05 | Records without usable SourceTimestamp quarantined with diagnostics | INV-016 |
| DR-008 | 2026-10-05 | Control/setpoint writes OUT-OF-SCOPE for initial release; read-only integration first | known-operations OPS-005/006/009/010 |
| DR-009 | 2026-10-05 | WGS decode via Nal; alp diagnostic-only until AQ-GAP-002 closes |
AQ-GAP-002 hypothesis |
| DR-010 | 2026-10-05 | WGH block value count derived from station CFG | AQ-GAP-003 hypothesis |
| DR-011 | 2026-10-06 | Umbrella roadmap established; D-001 recorded as the blocking decision | this document |
14. Unexpected findings
- Source document contains checksum/typo defects: MAT fetch request prints 557 (recomputes 540; 557 = SLT fetch checksum — copy-paste error), narrative destination mismatches (§2.2.3.1 "plant 89" vs telegram dest 86; §3.4.10.2 fixed-line dest given as plant number) — recorded in AQ-GAP-005/006.
- The PDF→markdown conversion is lossy at specific tables and truncates §3.7; byte-exact recomputation of long examples from the conversion is impossible (AQ-GAP-001/005). The PDF is authoritative.
- The §2.4 checksum algorithm verified exactly against all 35 single-line examples — including the subtle rules that spaces around
#are summed and Wait bytes are excluded.
15. Acceptance evidence
Production evaluation requires all of (implementation specification §77), evidenced by:
- Mandatory end-to-end scenario (§54 T0–T8;
software-specification.md§46): recorded as an automated acceptance test (T019); passing run attached to the Phase 14 gate. - Protocol traceability audit: every implemented operation maps to an
known-operations.mdentry with evidence; remaining gaps explicitly listed (§77 items 2, 15) — the gap registry is the evidence. - Vector suite green: all approved vectors passing in CI (§77 item 12).
- Restart/data-integrity tests (§53): no acknowledged history lost across restart, outage, backlog (items 7–9).
- Security tests (§55): untrusted certs rejected, None disabled in production config, no secrets logged.
- DoD checklist review: the 15 items of §77 walked item-by-item at G14, each with its artifact.
- Items 13 (validated against real equipment/traffic) and operational documentation remain post-simulator milestones dependent on field access — explicitly tracked, not silently dropped.
16. Plan maintenance
- Update §12 (Progress) at every phase gate; record new decisions in §13 immediately.
- Spawn a child ExecPlan (same structure, §59) for: any new AquaCom operation, storage/persistence architecture, OPC UA namespace redesign, security changes, cross-module refactors, data migration. Link children from §12.
- Move this plan to
docs/exec-plans/completed/when G14 and §15 are satisfied. - This plan never overrides the role-authoritative documents (
ARCHITECTURE.md§1).